Mumbai Metro 7A Viaduct May Need Reconstruction Over Missed OHE Height Requirements
The story in brief
Mumbai Metro 7A's viaduct may need reconstruction due to missed overhead electrification height requirements. MMRDA has addressed the issue with AAI and the Ministry of Civil Aviation since April 2024. Consultant SYSTRA-CEG-SMCIPL failed to highlight needed height increases for OHE poles, ranging from 0.025m to 2.244m. Airport Colony station meets limits, but the ramp needs an extra 2.4m. The matter remains ongoing as MMRDA awaits a final report.