Cauvery bridge repairs ongoing as work accelerates
The story in brief
The Cauvery bridge, built in 1963, is undergoing repairs after being closed on June 25. NHAI expedited work due to heavy traffic and the festival season, with repairs ongoing round-the-clock. Over 50% of work is complete, including replacing 120 bearings and 16 expansion joints. The bridge, last repaired in 2010, is being fixed at ₹10 crore. Work continues without hindrance due to absent river flow, with 60 bearings replaced and the rest expected in 15 days.