Aroor Railway Bridge Nears Completion as Piling Work Completes
The story in brief
The Aroor railway bridge, part of Kerala's Kumbalam-Turavur doubling project, is nearing completion with piling work almost done. Expected to cost ₹150 crore, it will be finished by March 31, 2028. Southern Railway reviewed progress, noting 90% land acquisition and 30% physical work done. The bridge, one of Kerala's longest under construction, is key to the 15.59 km project. Thiruvananthapuram Central's redevelopment, costing ₹438.95 crore, is the largest project.