Sanganoor Canal revamp awaits State approval
The story in brief
The Sanganoor Canal revamp project, aiming to create an alternative road corridor across Coimbatore, includes three packages covering 6.5 km from Rathinapuri to Trichy Road. The first package, costing ₹49 crore, was taken up in November 2021 and is nearing completion. The remaining two await state approval for ₹294 crore. Work paused in August 2022 due to relocation issues and resumed in June 2023 after plan changes. Officials remain cautious about early sanction.