WBPDCL seeks EIA bids for 800 MW Bakreshwar Power Plant
The story in brief
WBPDCL has invited bids for an EIA study of an 800 MW super-critical thermal power unit at Bakreshwar. The project is expected to require an investment of around Rs 10,070 crore and will be completed within four to five years. The EIA study will take about six months after the contract is awarded. The last date for bid submission is November 17, 2026. The next step is awarding the contract after evaluation of technical and financial bids.