B-SMILE reissues tender with lower cost estimates for two elevated corridors
The story in brief
B-SMILE cancelled tenders for two elevated corridors due to technical issues, then reissued them with reduced costs on the same day. The Minerva Circle corridor's cost dropped from ₹539 crore to ₹511.48 crore, while the Sholay Circle's fell to ₹515.28 crore. The UDD had flagged the hybrid tender model as a problem, affecting project timelines.