BMC warns of penalty for Versova STP delay

Source: Mid-day

The story in brief

BMC has warned of penal action if the Versova STP is not completed by March 31, 2027. The project, which will treat 180 million litres of sewage daily, is 80% complete. Additional Commissioner Abhijit Bangar inspected the site on October 14, 2026, and directed the contractor to increase workforce to 500 by October 31, 2026. The liquid line for secondary treatment is set to be completed by December 31, 2026, with full project completion by March 31, 2027. The project is expected to benefit residents of Versova, Andheri West, Andheri East, Juhu, and Vile Parle.