BMC Extends Flyover Repairs Deadline To March 2027
The story in brief
BMC revised repair plans for the Swaminarayan Flyover and three SCLR flyovers after an IIT Bombay assessment found worsening deterioration. The project cost rose 52% to ₹48.03 crore, with the deadline pushed to March 2027. The SCLR, a key link between Santacruz and Chembur, now faces extended repairs. The BMC seeks Standing Committee approval for an extra ₹16.26 crore.