
Kaveri TBM Breaks Through at Kilpauk Medical College Station
The story in brief
The Chennai Metro Rail Limited completed the tunnelling milestone for Phase-II Corridor-3 with the TBM 'Kaveri' at Kilpauk Medical College Station. The 685-metre tunnel between Chetpet and Kilpauk Medical College was executed by L&T, navigating five live Southern Railway tracks, a lake, and existing Phase-I Metro tunnels. The operation, which started on September 6, 2025, was completed in 252 days without major ground settlement.