BMC to Resume Concreting on Mumbai Roads by October 5, 2026
The story in brief
BMC plans to restart concreting work on 590 Mumbai roads by October 5, 2026, following monsoon withdrawal expected by October 8. Contractors have been reminded to begin work within the first five days of October. The project, costing Rs 17,000 crore, aims to improve road conditions and infrastructure. Work on 138 km of roads remains under the first two phases, with deadlines for completion by December 2026 and May 2027.